Work-to-complete list
A work-to-complete list is a list compiled by a contractor and issued to each subcontractor and their crews at, or near, completion. It is a list of the remaining items and any defective work that subcontractors required to complete before leaving the site.
The work-to-complete list, enables the contractor to formalise remaining work and ensure that subcontractors properly complete their contractual requirements before final payment is made and they move on to the next job. It can prove difficult to get subcontractors to return to a project once they have left.
The work-to-complete list is similar to the ‘snagging list’ or ‘punch list’, which is a list of faults identified by the appropriate certifying authority (typically the architect, contract administrator, or employer’s agent) which must be rectified before a certificate of practical completion can be issued.
Many contractors will wait for the the snagging list to be prepared before issuing their work-to-complete list. However, the earlier the subcontractors receive the list of remaining items, the sooner the problems are likely to be resolved.
The list should be clear, and very specific so there is no ambiguity about what needs to be done and where.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.